How it Works

Initiating

To be sure that FROG Homes can provide the optimum construction solution for client needs and the specific site, a FROG Homes Representative will undertake a preliminary site survey to determine feasibility and to prepare an accurate costing.

Where possible, we will require a copy of building plans of the existing site improvements but if, as is so often the case, original plans have been lost, we can also help in surveying existing structures and providing replacement drawings. Should you require further information, please contact us.

Preliminary

As soon as we know that we have the answer to client needs, we’ll undertake the next steps to:

Preparation

With Preliminary processes complete we will then:

Get in Touch

Reach out to us for more information and discuss your specific requirements.

Now We’re Ready to Go

With no unusual or uncontrollable delays, our entire construction program will be completed in 9 weeks from commencement on site to hand over of keys.
This broadly breaks down into 3 Stages:

Construction Stage 1

First 3 Weeks

Site Services
Foundation & Surface Bed
(The only Wet Trades)

Construction Stage 2

Second 3 Weeks

Superstructure
including Walls, Roof, Doors, Windows & Electrical First Fix

Construction Stage 3

Third 3 Weeks

Plumbing & Electrical Final Fixes, Tiling, Kitchen, Built in Cupboards and
All Other Finishes

Our 9 Week Site Program

Get in Touch

For more information, complete our enquiries form giving us your specific requirements.